How far in advance should I order windows and doors?

Short answer

Ask for a current lead time for the exact product, finish and glass, then work backwards from the date the opening must be weather-tight. Factory lead times vary by system, colour and schedule. Order only after survey, drawings and necessary approvals are settled; rushing manufacture around uncertain dimensions can cause a much longer delay later.

Planning this? Get a free, no-obligation installer recommendation

Work backwards from your weather-tight date — and remember survey starts the clock

Standard stock-colour uPVC
casementscasement: A casement is a hinged window opening, usually attached at the side or top of its frame. It opens rather than sliding vertically like a traditional sliding sash. The hinge position and opening direction affect ventilation, cleaning, clear passage and conflicts with paths, taps, curtains or furniture. More on casement
typically turn around faster than bespoke
dual-colourdual colour: Dual colour means that a window or door has different finishes on its outside and inside faces. It may be achieved through coatings, foils or separate components, depending on the material and system. Check what is visible at edges and when the sash or door is open, not only when closed. More on dual colour
aluminium, imported Nordic aluclad, curved or shaped frames, or specialist acoustic/solar glass, so ask each installer for the current factory lead time in writing. Crucially, the manufacturing clock rarely starts when you pay a booking deposit — it starts only after final survey dimensions and manufacturing drawings are signed off.

The extension and self-build trap: ordering too early versus too late

Ordering off architect's drawings before brickwork openings are formed risks frames arriving that do not fit actual tolerances; waiting until the roof is on before calling a glazing company can stall plastering and screed drying for weeks. The cleanest approach is to choose your supplier and confirm specifications early, hold a pre-order technical review with your builder, and book the final survey the moment openings are formed and finished floor levels are fixed.

Seasonal pinch points to plan around

Late summer through early November is traditionally the busiest installation period as homeowners race to beat winter weather, while factory shutdowns over Christmas and August can add two extra weeks to non-stock powder-coat or timber orders.

What to check

  • Ask for a current product-specific programme
  • Confirm the event that starts the lead time
  • Coordinate approved drawings, builder readiness and delivery access

Print this page to use the checklist on the day.

Questions people also ask

Does paying a deposit start production?
Not necessarily. Survey and drawing approval may still be required; ask which release point applies.
Can I order from architect's dimensions?
Only under an expressly agreed dimensional responsibility and check. Do not treat preliminary drawings as final manufacturing sizes.
Should I arrange fitting before delivery is confirmed?
Coordinate the programme with the supplier and installer and understand how provisional dates are changed.

Last reviewed:

Answered by the Windows & Doors Answered team. How we write answers · Corrections policy

Ask a free question

Didn't find your answer? Ask the team. The team usually replies within one working day.

Free guidance. No fees. No sales calls.

We use your question only to write back with an answer. Privacy policy.

Ask a follow-up about this page