Short answer

Send a numbered schedule, plans, elevations and key sections showing the wall build-up and frame position. Include performance needs such as
U-valuesU-value: A U-value describes how readily heat passes through a building element. A lower value means less heat loss through that element. For windows and doors, distinguish the complete assembly from the glass alone: a good glass figure does not establish the performance of the frame, edges and finished product. More on U-value
, security, acoustic and safety glass, plus colours, hardware and programme. State which items are fixed, which are open to alternatives and who checks final sizes. That allows quotes to be compared fairly.

Planning this? Get a free, no-obligation installer recommendation

Issue a numbered glazing schedule plus interface sections — not just GA elevations

An architect seeking comparable, reliable glazing tenders should send four things together: a numbered opening schedule (cross-referenced to floor plans and elevations), typical head/jamb/
cillcill: A cill is the lower projecting section beneath a window or door frame that helps shed rainwater away from the wall. It is also spelt sill. Its projection, joints and connection to the frame need to suit the wall construction, so water does not collect or run into vulnerable junctions. More on cill
and
thresholdthreshold: A threshold is the bottom part of a door set that you cross when entering or leaving. It connects the door seals, drainage and floor levels. A low or visually flush threshold can make movement easier, but it still needs an appropriate weather detail and a properly planned external water route. More on threshold
wall sections showing frame set-back, explicit performance targets (Uw,
g-valueg-value: A g-value describes the proportion of solar energy that passes through glazing into a room. A lower value means less solar heat enters, but it does not directly tell you how much visible light passes through. Consider it alongside light transmission, shading and the direction the glazing faces. More on g-value
, acoustic Rw,
PAS 24PAS 24: PAS 24 is a security test specification for complete windows and external door sets. It examines resistance to defined attack methods rather than promising that a product cannot be broken into. Evidence should relate to the actual system, configuration and hardware, not merely a lock or a broad product range. More on PAS 24
/AD Q, exposure class), and a clear statement of commercial scope (supply-only vs supply-and-install, craneage, membranes, and site survey ownership).

Why missing interface details skew tender prices

When tender packs omit finished floor levels, concealed blind boxes,
cillcill: A cill is the lower projecting section beneath a window or door frame that helps shed rainwater away from the wall. It is also spelt sill. Its projection, joints and connection to the frame need to suit the wall construction, so water does not collect or run into vulnerable junctions. More on cill
projections or structural steel deflection limits, cautious fabricators price contingencies while optimistic ones exclude them — producing a misleading spread that collapses into post-tender variations once detailing begins.

Require bidders to declare any system or sightline deviations

If you invite equivalent systems alongside a named reference profile, instruct every tenderer to list changes to frame
sightlinesightline: A sightline is the visible width of frame you see when you look at a window or door. Slimmer sightlines mean more glass and less frame. Makers sometimes measure it differently, so compare drawings of the exact products, especially where fixed and opening panes sit side by side. More on sightline
width,
thresholdthreshold: A threshold is the bottom part of a door set that you cross when entering or leaving. It connects the door seals, drainage and floor levels. A low or visually flush threshold can make movement easier, but it still needs an appropriate weather detail and a properly planned external water route. More on threshold
height, hardware type or glass build-up on a single deviations sheet so you can evaluate value engineering transparently.

What to check

  • Issue a numbered schedule with performance requirements
  • Include interface sections and installation scope
  • Ask bidders to list deviations from the specification

Print this page to use the checklist on the day.

Questions people also ask

Should I name a specific system?
Name one where it matters; otherwise set performance requirements and allow equivalents to be proposed.
Do I need full details at tender?
Key interfaces are enough for a reliable price. Final details can follow under an agreed design responsibility.
Who should check site dimensions?
Agree it at tender. Usually the installer measures the built openings before manufacture.

Last reviewed:

Answered by the Windows & Doors Answered team. How we write answers · Corrections policy

Ask a free question

Didn't find your answer? Ask the team. The team usually replies within one working day.

Free guidance. No fees. No sales calls.

We use your question only to write back with an answer. Privacy policy.

Ask a follow-up about this page