Lead times: when to order, and why it varies
Free guidance. No fees. No sales calls.
Short answer
Plan the order backwards from the required installation date, allowing for survey, drawings, approvals, manufacture, glass, delivery and site readiness. Ask which event starts the quoted lead time and what can delay it. Factory lead times vary with system, finish and current demand. Keep the programme updated after changes and do not approve unchecked dimensions to gain time.
Planning this? Get a free, no-obligation installer recommendation
The ordering answer explains why programmes vary; this guide creates a project-specific sequence from early enquiry to fitting. A supplier's manufacturing estimate may exclude survey, drawing revisions and specialist glass. The glazing programme also depends on the builder delivering safe, level, accepted openings and access at the right time, not only on the factory finishing frames.
1. Set the real installation need
Identify when the building must be weather-tight and what work depends on glazing being installed. Include plaster, flooring, kitchen delivery and occupancy rather than choosing a date in isolation. Ask the builder when structural openings and levels can be checked. If temporary closing or heating is needed while waiting, assign responsibility and budget rather than assuming the glazing supplier provides it.
2. Ask what starts and stops the clock
Get separate stages for enquiry, specification, survey, drawings, approval, manufacture and delivery. Under Section 28 of the Consumer Rights Act 2015 (legislation.gov.uk, checked 2026-11-24), goods must be delivered within 30 days unless a longer delivery period is expressly agreed, and Section 52 requires services to be carried out within a reasonable time if no date is fixed. Under Regulation 28(1)(b) of the Consumer Contracts Regulations 2013, made-to-measure windows and doors are exempt from the 14-day cancellation right once ordered to your specification. Specialist glass adds factory time too — for example, Morley Glass publishes a 10 to 12 working day production lead time for Uni-Blinds sealed units (morleyglass.co.uk) — so ask each installer for the full factory-to-fitting timetable in writing.
Before moving on
- The installation date matches building dependencies
- The lead-time starting event is written down
- Site verification happens before manufacture approval
Print this page to use the checklist on the day.
3. Coordinate approval and site readiness
Allow time for the designer, energy assessor or authority to review changes where required. Freeze openings, , glass and colours before manufacture instead of approving uncertain details to chase a date. Agree unloading, lifting, access, storage and who accepts the prepared openings. Check when temporary protection is removed so a missed delivery does not leave an unsafe or insecure building.
thresholds
threshold: A threshold is the bottom part of a door set that you cross when entering or leaving. It connects the door seals, drainage and floor levels. A low or visually flush threshold can make movement easier, but it still needs an appropriate weather detail and a properly planned external water route. More on threshold4. Manage changes and delivery evidence
Record the confirmed programme and ask for updates when drawings, finishes or site conditions change. Agree how delays and revised dates are communicated and whether partial delivery helps or complicates fitting. Inspect delivered items against the schedule and confirm the installation appointment only when the site and products are ready. Keep the final programme with payment milestones and handover obligations.
Your project checklist
- Separate all programme stages
- Check special finish and glass dependencies
- Allow for design review
- Agree temporary weather protection
- Plan unloading and lifting
- Record revised dates and payment effects
Print this page to use the checklist on the day.
What to do next
Make a backwards programme from weather-tightness and ask the supplier and builder to confirm each dependency. Resolve uncertain dimensions and approvals first. Update the dates after every specification change and authorise manufacture only once the verified schedule and site-readiness plan agree.
Relevant answers and comparisons
Useful tools
Related pages on this topic
Questions people also ask
Does the lead time start when I enquire?
Usually it is tied to a later agreed event such as approved drawings or payment. Ask the supplier to state the actual starting point.
Can I speed things up by skipping survey?
That can create size and responsibility risks. Only use an alternative dimension-verification arrangement that is clearly agreed and appropriate to the project.
What if the frames are ready before the site?
Agree secure storage, protection, handling costs and revised fitting dates. Do not unload fragile products into an unprepared or unsafe location.
Last reviewed:
Answered by the Windows & Doors Answered team. How we write answers · Corrections policy
Related
Ask a free question
Didn't find your answer? Ask the team. The team usually replies within one working day.